StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

Congressman Womack Demands Answers from DOE on Clean Line's Sec. 1222 "Partnership"

1/17/2015

1 Comment

 
Arkansas Congressman Steve Womack seems to be tired of being put off by the U.S. Department of Energy.  On Thursday, the Congressman sent a letter to Secretary of Energy Moniz, demanding a meeting to get the answers about Clean Line and Section 1222 of the Energy Policy Act that he has been denied on two previous occasions.
Secretary Moniz:

I have now written you in August 2013 and September 2014 regarding the Department of
Energy's (DOE's) consideration for a partnership with Clean Line Energy Partners through the Plains & Eastern transmission line project and have yet to receive a satisfactory answer to my questions.

Since the date of my previous inquiry, I understand that the Draft Environmental Impact Statement (EIS) has been released for public comment, at which point, in accordance with your latest response to my office, "DOE will consider questions such as those raised in [my] letter."  Unfortunately, merely acknowledging this fact does not, in turn, answer the questions raised.

As you know, the path of the proposed transmission line runs directly through the Third District of Arkansas. Therefore, I am extremely concerned about Clean Line's authorization.  Respectfully, I am also very frustrated by one of your Department's disingenuous responses to my letters that identified "public interest" as one of the considerations given to the Clean Line
application.
There has been an astounding lack of assurance that my district - and the State of Arkansas- will have any interest in this project at all and no guarantee that Clean Line will supply power to my constituents and my state. I place further emphasis on this concern given the denial of a Certificate of Public Convenience and Necessity from the initial application Clean Line had submitted to the Arkansas Public Service Commission.

Section 1222 of the Energy Policy Act of 2005 has never been invoked for the approval of an
electric power transmission facility. In light of the uncertainty of this process and the Section
1222 application, in addition to a lack of assurance regarding the benefit for the state of Arkansas from such a transmission line, I must again ask the following:

• What guarantee might the citizens of the Third District be afforded when it comes to a
specific energy supply to our state rather than a highway for power to Tennessee?
• How does the Department of Energy determine its authority for partnership with a private entity and the application of supposed rights to eminent domain?
• What factor does the denial of Clean Line as a public utility in the State of Arkansas play
in the final decision by the Department of Energy?

The DOE has been less than forthright in providing answers to the legitimate questions raised regarding Clean Line. Therefore, at this time, I would like to request a formal meeting with you to not only discuss these questions, but also the unacceptable responses that have been sent to both my office and stakeholders within the Third District. I look forward to your prompt reply.
Congress created Sec. 1222, Congress can take it away.

Something fishy is going on here...  maybe it's time to start an official investigation into the way DOE has been handling the Clean Line matter.  I'd start by asking them why the "Management Committee" as described in section 8a of Contract No. 1 between Clean Line Energy and the DOE, the Advance Funding and Development
Agreement Plains and Eastern Clean Line Transmission Project
, has not been meeting quarterly as stipulated in the agreement.
1 Comment

Centralized Wind's Race to the Gold

1/17/2015

5 Comments

 
Will the U.S. ever get an offshore wind industry started?  One step forward, two steps back.  Just when Cape Wind might finally lay oar to the water, the utilities that signed power purchase agreements to purchase it have canceled their contracts, saying that Cape Wind failed to meet its obligations under the contract.  Cape Wind says the contracts are still valid, citing force majeure.  The companies are further squawking because they were "forced" to sign the power purchase agreements to get the state of Massachusetts to approve their merger. 

The article forgot to mention that the company has made a $40M investment in hundreds of miles of transmission lines for onshore wind since the power purchase agreement was signed in 2010.  Did National Grid cancel its contract with Cape Wind in order to stifle competition to its investment in Midwest wind?

Offshore wind continues to struggle, while Midwest wind is trying to court the U.S. Department of Energy to invoke an as yet untested section of the Energy Policy Act to "participate" in the Clean Line projects in order to usurp state authority to site and permit them, and use federal eminent domain to take land Clean Line was denied by the states.  Clean Line's projects have not been reviewed or approved in any regional transmission planning process under FERC's Order No. 1000's competitive transmission scheme.  The proposed action of the DOE would not only put the federal government in the business of transmission planning, it would also actively interfere with electric markets, two areas where the DOE does not have jurisdiction or expertise. 

Why is Midwest wind a bad idea?  Because it's located too far away and building overland transmission simply to ship electricity to the east coast is expensive, time consuming, and unfair to landowners crossed, who will receive none of the benefits, but all of the burden.

Why is offshore wind a good idea? 
Responsibly developed offshore wind power offers a golden opportunity to meet our coastal energy needs with a clean, local resource that will spur investments in local economies - creating unparalleled job growth and avoiding the need to export hard-earned energy dollars outside the region.
Or so says a mid-2014 report from the environmental community, Catching the Wind.  But yet, some of the same groups who touted the benefits of offshore wind in this report were simultaneously intervening in Midwestern wind transmission line cases and telling state utility commissions that there's a "need" for Midwestern wind on the East coast.  So, which is it?

Or is the Sierra Club just a bunch of hypocrites?  I'm leaning toward that hypothesis, since the Sierra Club is all over the map on the issue of eminent domain for energy projects, as pointed out by an Arkansas landowner.
The eminent domain issue has become a key point of contention between Pilgrim and the Sierra Club. An attorney for the Sierra Club has said that Pilgrim has no rights of eminent domain because it is a private company and not formally designated as a utility by the Board of Public Utilities.
But yet, the Sierra Club thinks that Clean Line, a private company not formally designated as a public utility in Arkansas, should use eminent domain as "the middle ground" to take the rights of way it finds necessary through the state.
On the other side are landowners who see the power lines marching across their land as more big government intrusion into their lifestyles and even interfering with their livelihoods.

Additional arguments against construction of the lines are possible health effects, and the fact that the entities proposing the construction are private companies.

It seems strange an argument against private industry would be made. The United States to a very large degree operates that way. It’s capitalism, right?

Rights of way must be secured for these power line projects private or otherwise, just as any project in the public interest such as a toll road or a railway. Fair market price must be paid for any property taken for rights of way.
I think the Sierra Club is an opportunist, using whatever arguments it thinks will delay or alter energy plans it does not like (those involving fossil fuels).  Sierra Club has no qualms about using landowners as pawns to further its environmental agenda and has shown it will jump on board even the worst energy projects, if they are only cloaked in "clean" labels.  Sierra Club needs to develop a rational and coherent energy policy and stick with it because people are abandoning the club in droves.  Maybe Sierra Club thinks that's okay, since it can more than make up for the members it loses with more grant money from big, mysterious, "environmental" funds.  However, true grassroots integrity shall remain elusive.
Let's get on with the offshore wind, shall we?  If the East coast wants "clean" power, they need to make it in their own backyard.  Once they get over the initial direct cost shock (as opposed to the hidden incremental cost increase of building new transmission lines across the country -- they're not going to avoid the costs), they may realize that being clean and green and responsible for their own environmental footprint provides other social and economic benefits as well.
5 Comments

Get Your Clean Line Plains & Eastern EIS Comments In!

1/17/2015

2 Comments

 
In setting national environmental policy to improve and coordinate Federal plans, functions, and programs, Congress recognized that each person should enjoy a healthful environment and that each person has a responsibility to contribute to the preservation and enhancement of the environment.

The policies and goals of National Environmental Policy (42 U.S.C. § 4331, Congressional declaration of national environmental policy) are intended to:
(1) fulfill the responsibilities of each generation as trustee of the environment for succeeding generations;

(2) assure for all Americans safe, healthful, productive, and esthetically and culturally pleasing surroundings;

(3) attain the widest range of beneficial uses of the environment without degradation, risk to health or safety, or other undesirable and unintended consequences;

(4) preserve important historic, cultural, and natural aspects of our national heritage, and maintain, wherever possible, an environment which supports diversity and variety of individual choice;

(5) achieve a balance between population and resource use which will permit high standards of living and a wide sharing of life’s amenities; and

(6) enhance the quality of renewable resources and approach the maximum attainable recycling of depletable resources.

The intent of Congress seems to have been lost in the creation of the Plains & Eastern Draft Environmental Impact Statement.  Consideration of these goals should be evident, but the closest the Statement comes to evaluating these issues is in Chapter 3, Section 3.5, Environmental Justice. However, that section simply consists of bureaucratic “box checking” with its tables of racial and economic statistics and finding of “no significant impacts.”

What our federal government failed to consider in its study are the very real impacts the Plains & Eastern project (P&E) will impose on one segment of society for the sole benefit of another.  That the beneficiaries of the Plains & Eastern project are intended to be economically advantaged and politically influential eastern cities with a “green” conscience, and that the ones who must make the social and economic sacrifice to meet this need are rural landowners without political clout does not seem to have been of moment in the study.

Rural landowners and farmers have been fulfilling their responsibilities as trustees of the land that feeds us all for generations.  P&E will interfere with their responsibilities.  In addition, P&E will also interfere with their ability to make a living, bisecting small farms that provide income and/or real estate investment wealth to those who depend on their land for economic purposes.

P&E will preclude the ability of rural landowners in Oklahoma and Arkansas to live in safe, healthful, productive, and esthetically and culturally pleasing surroundings as unsightly, gigantic transmission lines may endanger their well-being and interfere with their productivity and sense of place. 

P&E is not without environmental effect.  Weighing the destruction of one part of the environment to benefit another is not a matter of simple trade offs when there are other options available that are not as damaging to the environment.  P&E has not been determined needed to meet any identified public policy goal by any authority tasked with planning the electric grid.  P&E has no customers.  Other options exist for eastern cities, such as offshore wind, local solar, or other local and regional renewable energy projects that provide local jobs and economic stimulation.  Americans are not being given a choice, where market forces determine their best option.  Participation in P&E by the Department of Energy is a top-down, government-forced “solution” to a problem that does not exist.

P&E will affect the historic, cultural and natural aspects of the rural environment, causing rural landowners to sacrifice for the needs of eastern cities.  There is no balance here, all the sacrifice is coming from one segment of society, while all the benefits flow to the other.  What are eastern cities willing to sacrifice for their “green” conscience?  Atlantic offshore wind has been struggling to be built for years, but rejected time and again for esthetic or cost reasons.  When eastern cities are faced with having to live with the infrastructure that supports their habits, they reject it in favor of other solutions.  When those solutions remove the sacrifice, but not the benefits, to rural landowners in other states, the intent of national environmental policy is forgotten.  This paradigm has existed for decades, where Ohio Valley residents have sacrificed their health, environment and economic interests to mine and burn coal that is turned into electricity and transmitted to eastern cities.  P&E is just more of the same sacrifice of one segment of society for the needs of another.

There is no balance to be found between population and resource when the needs of the many continually override the needs of the few.  No Americans are disposable at the whim of others, no matter the color of their skin or their economic position.  Wide sharing of life’s amenities requires that each person accept responsibility for their own needs.  If eastern cities require cleaner energy, they have the ability to create it themselves, and in fact, many already are doing so.  Top down government solutions, such as P&E, are inconsistent with individual choice.

Rural America is a finite resource that is fast disappearing and must receive careful consideration in DOE's EIS.

I believe the underlying mission of the federal government has been forgotten in the preparation of the EIS and, instead, a blinders-clad bureaucracy has simply proceeded through the motions of preparing it without considering its purpose.  P&E is asking the federal government to wield the sledgehammer of eminent domain to force its project on a rural America that has rejected P&E.  Integral to the big picture is the fact that P&E is nothing more than a business plan, an idea for profit, and does not fulfill any identified reliability, economic or public policy need.  There is no amount of sacrifice that is acceptable for the pecuniary interests of private investors.

Don't forget to file your EIS comments here!
  Deadline is March 19!
2 Comments

Transmission Politics

1/8/2015

1 Comment

 
Coming across common themes over and over tells me something... maybe I should write about it?

I've seen a whole bunch lately about the politics of transmission line proposals, more precisely how politics affects the state public utility commission process.

This morning, I read something that pushed the issue into blog post status.

Iowa Governor Terry Branstad has warned his state legislature not to interfere in the business of the Iowa Utilities Board.
Branstad, who appoints the members of the utilities board, warned against "political interference" into the administrative review process by which a pipeline carrying Bakken crude oil and a transmission line transporting wind-generated electricity could be approved.

"It would be mistake to get politics into this," Branstad said. "We should abide by the processes that have been put in place."
Maybe Branstad doesn't understand those "processes?"  Our government is separated into three branches:  The Executive Branch carries out existing laws and recommends (but does not alone create) new ones.  It administers our government.  The Legislative Branch makes laws, at the will of the people it represents.  The Judicial Branch interprets existing laws.  Branstad is a member of the executive branch.  The Iowa legislature is a member of the legislative branch.  The IUB is a member of the judicial branch, although unlike a regular court, a utility board can make up copious rules about how they're going to carry out the laws made by the legislative branch.  Trying to figure out which one is more powerful is an exercise in futility... and politics.

Branstad, as Governor, appoints the members of the IUB.  This is a political process.  A member of the executive branch will appoint those he believes will carry out his mission.  Once appointed, IUB members are supposed to serve independently as they interpret utility laws, however, a crafty governor can control this process by allowing appointments to expire while the incumbents continue to serve at the daily whim of the governor, who can remove the incumbent and replace him at any time.  I have no idea if this is the situation in Iowa, but I have seen just this situation perpetuate in several states.  When it happens, the judicial branch comes under the thumb of the executive branch and can be easily influenced to make certain decisions on a political basis in order to remain in place.

The legislature makes the laws that direct the actions of an independent, quasi-judicial utility board.  The judicial branch cannot create laws, but receives its marching orders from the legislative branch.  If the legislature is displeased by the actions of the Board, it can make new laws to shape the decisions of the Board.  In this way, the legislature can influence the judicial branch.  However, there's more protection on this side of the coin, because the legislative branch is operating at the will of the people, and must obtain consensus from many to create new laws.

I don't know why Branstad believes it's not already "political."  The state utility board process is about as political as it gets.  While he warns the legislature not to get involved in a situation he controls, what the legislature eventually does will be political.  It's all political!

So, if you want to influence your state utility board process, you must engage in politics.  You can talk to your legislators to gain their support to make new laws that guide the decisions the utility board makes.  You should probably talk to your governor about refraining from getting involved in the utility board processes.  Branstad has it completely backwards!

Politics is described as:
the activities associated with the governance of a country or other area, esp. the debate or conflict among individuals or parties having or hoping to achieve power:
Companies proposing new transmission projects hope to influence the judicial process as much as individuals or groups opposing the transmission project.  In order to do so, they push the legislative or executive branch to shape the judicial decision.  Despite plenty of denial, the judicial processes of a utility board are heavily influenced by politics.  It's the reason transmission developers spend so much lobbying your representatives to support their projects AGAINST YOUR WISHES!

Public opinion drives political decisions.  A legislator is carrying out the will of the people.  If enough people become involved in a utility board process, they can shape the process through their legislators, who may be more interested in their duty to the people than the free lunches and campaign contributions transmission corporations provide.  The bigger the public push back, the better your chances.

Transmission developers also court other groups and individuals to take a position supporting their proposal.  Sometimes a quid pro quo situation develops.  This happens because a utility board is unlikely to approve even the best project if it is under political fire not to do so, therefore the transmission developer needs allies to create, at least, an appearance of support.

So, can a large, loud uprising of the people affect the decision of a utility board?  You bet'cha!  But don't get confused by the difference between public opinion and public comment.

Public opinion is an aggregate of public comment.  The public comments citizens make to a utility board, in isolation, rarely drive the decision of the Board because they are typically not based on legal arguments about the laws the Board must follow in its findings.

Utility law guru Scott Hempling recently pondered the effectiveness of public comments in his monthly essay.  This month, he featured several questions that he will use as projects for his utility law students.  Here's one:
Engaging the public:  Candor requires an admission:  The lay citizenry's views do not count as "substantial evidence," required by courts to sustain agency orders.  Does that fact make public hearings (i.e., the non-technical hearings) shams?  If not, then what is the value of public participation?  What are ways to create that value, at reasonable cost?   Traditionally, agencies announced public hearings in the newspaper's "legal notices."  How useful is that approach today?  What are an agency's responsibilities to educate the public and seek its views?
The "substantial evidence" Hempling mentions must come through the legal process, either through an attorney or individuals acting pro se.  While a utility board's decision is politically-driven, it must back up its decision on a legal basis.  The utility provides its proposed legal basis for approval through the evidentiary hearing process.  Opposition must therefore provide its own legal basis for denial in this same venue.  The utility board, thus armed, can choose from whichever body of evidence it needs to to back up its decision (and hopefully make it stick.)  It's pretty hard to make a decision that's not legally sound stick through appeals.  It would be doubly-hard for a utility board to make a decision that denies evidence of future reliability issues coming from a supposedly independent third party, such as a regional transmission organization.  Therefore, a utility or RTO may choose to find new information upon which to withdraw its proposal, instead of forcing a utility board into a denial.  But, again, this is a political process that takes place that allows utilities to withdraw and save face (and money, but that's another story).

So while your own individual comment may not carry much legal weight, when combined with the comments of thousands of others, it is a very powerful, political tool!

If Branstad truly wants to keep "politics" out of utility board decisions in Iowa, he should start a little closer to home.  The legislature, as the body tasked with making laws, can make any laws it chooses, whether Branstad likes them or not.  Sure, he could veto a new law, but doing so to a new law widely supported by the people would come at his own political peril.
"Never doubt that a small group of thoughtful, committed citizens can change the world;
indeed, it's the only thing that ever has."
- Margaret Mead
1 Comment

"A Significant and Unwarranted Intrusion"

12/31/2014

1 Comment

 
Just one more post about Requests for Rehearing of the Illinois Commission's issuance of a conditional permit for the Rock Island Clean Line.

The Illinois Landowners Alliance not only reiterates the arguments put forth by ComEd and the Illinois Farm Bureau, but adds a stylish lambasting of the Commission for permitting "a significant and unwarranted intrusion upon landowners."
ILA’s witnesses and its many other members have expressed repeatedly their uniform opposition to the Project, routing and treatment of landowners and their concerns. The Order’s granting of a CPCN to Rock Island will permit Rock Island to force its way onto landowner property to “make land surveys and land use studies” (220 ILCS 5/8-510), a significant and unwarranted intrusion upon affected landowners for a project that is so speculative and tenuous.
Although the ICC significantly conditioned RICL's permit before any actual construction begins, and denied them eminent domain authority at this time, the ICC also allowed RICL immediate access to private property to conduct its "surveys."

It's a powder keg.  Let's hope it doesn't explode before the ICC reconsiders its misguided decision to order the trespassing and destruction of private property by a company with no financial assets.  The landowners don't seem to have changed their opinion about RICL and probably aren't going to welcome them to their properties with open arms and a forgiving attitude.  I hope the ICC thinks this though...
1 Comment

How Transmission "Competition" Hurts Reliability and Costs Consumers More

12/31/2014

3 Comments

 
FERC is in love with the idea that "competition" between transmission developers will result in lower costs for consumers, but that's not necessarily true.  While competition between developers for a project identified in a regional plan could provide lower cost projects, it completely fails when developers create and submit projects before any need for them is independently recognized by the RTO, or when merchant developers propose transmission projects outside of regional plans.

Hopefully we've seen the last of the transmission projects designed simply to increase profits for a vertically integrated utility that is conceived before the RTO determines a "need" for it.  In this cart before the horse scenario, the RTO will create a smokescreen of need for an unneeded project and "order" it to be built.    These projects usually fall apart when they are examined with any amount of sincere effort.  When this happens, the RTO will cancel the project, but not before millions are spent for a transmission project that will never be built. 
When an RTO "orders" a project, its cost is allocated to ratepayers in the region.  How much are ratepayers paying each year for cancelled projects resulting from bad planning?

But an even more serious problem is developing as a result of merchant projects proposed outside the regional planning process.  These projects are never submitted into the regional planning process, therefore there is no need for them, either reliability, economic or public policy.  The only review they get from regional planners looks at how their interconnection will affect reliability.   These projects are not "ordered" to be built by regional planners. They are constructed at the expense and initiative of their owners, who recoup their costs through charging negotiated rates for transmission service.  The only goal of merchant lines is to make money.  If they aren't economically feasible, they won't be built.  The choice to build them lies entirely with their owners, even after they have a permit in hand.

But a merchant project proposed outside the regional planning process is never "ordered" and must prove itself "needed" to state and federal regulators in order to receive necessary permits or eminent domain authority.  In that instance, the state or federal regulator is stepping into the regional planning position to determine the need for a transmission project.  State and federal regulators are ill-equipped to make such a determination because they lack the kind of expertise found at an RTO.  The best a regulator can do is rely on the evidence submitted by experts in the case.  Merchant transmission developers can afford any number of experts who will say whatever they're paid to say.  Regulators can only afford in-house expertise, or rely on the experts hired by other parties. The decision is not based on any inherent knowledge, but on expert testimony.

So, what happens when a state finds a merchant transmission project serves some purpose and issues it a conditional permit to construct?  Now we've got two competing regional transmission planners with different projects in their plan.  The RTO version of the plan includes projects it has ordered that it has determined are needed for reliability, economic or public policy purposes, and these projects are being paid for by ratepayers.  The state uses the same plan, but it also includes the permitted merchant project, that doesn't serve any RTO-identified need.  Isn't this too much transmission?

What happens to the ordered regional plan if the merchant project is constructed?  Sometimes this effect is modeled into the plan so that other "ordered" projects may not be needed after all.  A permitted merchant project could cause cancellation of transmission projects in the regional plan before they are completed (but long after they start collecting their costs from ratepayers).  But, remember, a merchant project that has not been "ordered" by a RTO may never be built.  So, if a merchant project causes the cancellation of one or more RTO projects, it could jeopardize reliability if it is suddenly abandoned by its developers before being built.

Dilemma!  Perhaps FERC should take notice of the mess it has created and find a remedy.  I would suggest that projects must be part of a regional plan (whether RTO/ISO or other existing planning authority), and that unneeded merchant projects be prohibited.

Think I'm just nuts?  The Illinois Commerce Commission's recent conditional approval of the Rock Island Clean Line merchant transmission project is already causing doubt about other regionally planned transmission projects that are currently before the ICC.  As the Illinois Farm Bureau pointed out in its recent request for rehearing of the RICL decision, the RICL order is already having "a negative impact on consumers."  The IAA says that the RICL approval is having an immediate effect on two other transmission projects currently before the ICC, a MidAmerican project and an Ameren project, where the ICC staff has suggested that RICL's approval draws into doubt whether these two projects are needed.  And who pays for the other two regionally planned projects if they are cancelled by RICL?  Consumers.
As multiple intervenors have pointed out in this docket that Rock Island’s failure to produce a needs analysis from PJM and/or MISO hurts all of the stakeholders, it seems like this problem could have easily been avoided. The absence of this global analysis produces increased unpredictability and either slows or jeopardizes other legitimate transmission projects. This risk to the consumers could have easily been prevented.
In addition, the IAA points out that there has been no comparative analysis by the ICC as to which of these projects are necessary to promote the development of an effectively competitive electricity market that operates efficiently, are equitable to all customers, and are the least cost means of satisfying those objectives.  Regional planners say that the MidAmerican and Ameren projects are the best options.  The ICC has determined that RICL is the best option, without any attempt at making a fair comparison.

So, what shall it be?  Should we cancel regionally planned projects that conflict with merchant plans and hope the merchant projects are eventually built?  Will the lights go off if none of them get built?  We simply cannot have it both ways. 
Now, other potentially viable and successful transmission projects will have to wait on the sidelines to see if Rock Island can get its act together by, among other things, finding money, qualified employees, suppliers, and numerous regulatory approvals. None of this benefits Illinois consumers, the market, or the reliability of the electric system. Instead, it puts everything at greater risk.
Independent transmission projects based on greed are now actively hurting consumers.  This game must stop.
3 Comments

Grassroots Group Defeats AEP Transmission Project in Arkansas

12/30/2014

0 Comments

 
Save the Ozarks is celebrating a big victory in Eureka Springs, Arkansas, this evening!

Today, AEP subsidiary Southwestern Electric Power Company (SWEPCO) withdrew its application for a permit from the Arkansas Public Service Commission, citing:
SWEPCO received a notification letter from SPP stating that updated electric load  forecasts showing lower future electric demand in North Arkansas than prior forecasts for the area critical to the Facilities, and the  recent cancellation of several large, long-term transmission service reservations, establish that the Facilities are no longer needed to meet the reliability needs in the region.
The withdrawn transmission project was a 60-mile, 345kV monster proposed to plow through the Ozarks as part of a plan developed in 2007.  2007?  That's 8 years ago!  Isn't it funny that SPP continued to find a need for this project, until the Arkansas Public Service Commission made clear that it wasn't likely to approve it.  Suddenly, SPP had an epiphany on load forecasts and transmission service reservations.  How convenient.  Except, that's exactly the same thing that happened with AEP's PATH transmission line when  Virginia state regulators became suspicious and ordered further studies by regional grid planner PJM Interconnection.  This is how a regional planning organization and a transmission owner fall on their collective sword.

How are electric consumers supposed to believe a thing these transmission cartels say anymore?  It's quite clear that transmission planning organizations are conditioned to simply rubber stamp the transmission building whims of their members.  If nobody resists, then the project gets built.

However, the folks of NW Arkansas resisted... and formed Save the Ozarks.  Under the competent leadership of Pat Costner, retired Greenpeace scientist, Save the Ozarks demonstrated that it takes a big, loud, committed, very public opposition, along with competent legal representation to defeat a transmission line.  Lawyers, legal processes and polite demurral to power company public relations campaigns alone do not win transmission permitting battles.  It's about making the transmission project political poison and telling the public the truth.  Pat knew exactly what to do and she did it with style and dignity!

So, Congratulations, Save the Ozarks!  Enjoy your victory for a few days before you start wondering about who is going to pay for SWEPCO and SPP's big "oops."

And for my "friends" at AEP... here's mud in your eye!

"Never doubt that a small group of thoughtful, committed citizens can change the world; indeed, it's the only thing that ever has." - Margaret Mead
0 Comments

How Deep is the Clean Line Corruption at the U.S. Department of Energy?

12/15/2014

5 Comments

 
Get out your hip-waders, folks, it's going to get pretty deep!

According to this article, in 2011 former Secretary of Energy Steven Chu appointed Lauren Azar to a position at the DOE in order to carry out the administration's political agenda. 
Chu's selection of Azar was largely seen as a sign of the Obama administration's intense interest in expanding the grid to support renewables and tackle climate change, sources said.
Azar got the finger pointed at her as the impetus for a controversial memo that urged federal power marketing agencies (PMAs) to use their authority to help get privately funded transmission projects built.
As laid out in the memo, she also championed Texas-based Clean Line Energy's application to partner with DOE through its never-before-used authority under Section 1222 of the Energy Policy Act, which would allow a PMA with federal authority to site the line and overcome state opposition.
It's not about reliability or economics of the grid, it's about federal support for certain companies with personal ties to the DOE:
Jimmy Glotfelty, founder of Clean Line Energy Partners and a former senior electricity adviser for President George W. Bush, said Azar should be remembered for trying to build infrastructure and integrate renewables in a thoughtful and cooperative manner.

"The customers of PMAs are pretty protective, and if you ask a lot of people who have been in her shoes -- including myself -- it's not uncommon to get into debates with customers of PMAs," he said. "They're tough negotiators."
Clean Line, with its DOE-connected "vice president," became the only transmission company to take advantage of Sec. 1222 of the Energy Policy Act of 2005 during a very convenient RFP process run by the DOE in 2010.  But the pre-Azar DOE just wasn't aggressive enough:
Azar brought that same spirit to DOE. She helped bring together the "federal family" in 2011 -- nine agencies key to streamlining federal permitting of major new power lines that could have taken up to 15 years to garner approval (Greenwire, Oct. 5, 2011). DOE already had existing authority to do so under 216(h) of the Energy Policy Act of 2005, language that allows the agency to coordinate federal and environmental reviews.

"DOE, until I got there, implemented [the rule] in somewhat of a tepid manner," she said. "I came in like gangbusters as I always do and not only helped to lead the rapid respond team for transmission but helped DOE draft some rules for 216(h), negotiate with the nine agencies."
Shortly after Azar was appointed, Clean Line submitted an "updated" application under Sec. 1222 in order to use the federal power marketing agencies to take land for its private gain and override state denials.
The Honorable Lauren Azar
Senior Advisor to the Secretary
U.S. Department of Energy
1000 Independence Avenue SW
Washington, D.C. 20585

August 17, 2011

Dear Lauren,

With development efforts well under way, the Plains & Eastern Clean Line is positioned to
help meet President Obama's call for 80% clean energy by 2035. The Plains & Eastern Clean Line will provide affordable, renewable power to millions of customers in the  southeastern United States. Regulatory and permitting approvals at the state and federal levels are the critical path items. Since submitting a proposal in July 2010, the Plains & Eastern Clean Line has made substantial development progress, strengthening the case for a partnership with the Department of Energy (DOE) and Southwestern under  Section 1222 of the Energy Policy Act of 2005.

The attached document provides an update on our efforts, including the widespread support the project has received from a diverse group of stakeholders. It also supplements the original application with respect to how the project is necessary to accommodate the increase in demand for transmission capacity and how the project is consistent with needs identified in transmission plans or otherwise by the appropriate transmission organization.
Projects like the Plains & Eastern Clean Line have the potential to return the United States to a global leadership position in clean energy. The private sector has the resources and the desire to invest in our aging infrastructure and we respectfully ask that the DOE exercise its authority to make it possible. We  appreciate the attention you are giving the Plains & Eastern Clean Line. We will be in Washington, DC regularly in the coming months and would like the opportunity to sit down with you and your team to review the project materials and respond to any  questions.
Magically, the DOE entered into an Advance Funding and Development Agreement with Clean Line in early 2012, despite the fact that Clean Line did NOT meet all the statutory criteria in Sec. 1222.  Sec. 1222 requires that a project:
2) is consistent with--
(A) transmission needs identified, in a transmission expansion plan or otherwise, by the appropriate Transmission Organization (as defined in the Federal Power Act [16 U.S.C. 791a et seq.]) if any, or approved regional reliability organization
Clean Line's projects are not a part of any transmission expansion plan, therefore they cannot be "consistent with" a plan that does not include them. 

Instead, the DOE relied on:
DOE has emphasized the need for additional high voltage transmission capacity to deliver renewable resources from transmission-constrained areas, stating in its "20% Wind Energy by 2030" Report that "If the considerable wind resources of the United States are to be utilized, a significant amount of new transmission will be required."
GRID2030 is probably the highlight of Clean Line "vice president" Glotfelty's career at the DOE.  And then Glotfelty leaves the DOE after setting the stage, and personally invests in Clean Line Energy Partners? 

Clean Line brags:

Jimmy worked for George W. Bush, for almost eight years, at both the gubernatorial and presidential levels. He led the Bush Administration’s efforts on electricity issues with Congress and the electric utility industry.  In this capacity, he founded Office of Electric Delivery and Energy Reliability at the Department of Energy (DOE) and served as its first Director.
Let's see... which office is undertaking DOE's consideration of Clean Line's application under Sec. 1222? 
The Department of Energy’s (DOE) Section 1222 Program is administered by the Office of Electricity Delivery and Energy Reliability (OE).
Wow!  What a coincidence!  A DOE appointee uses his office to set up a scheme whereby private investors can override state authority and regional transmission planning processes, and then leaves his position to personally invest in just such a scheme?  And the office he "founded" is now in a position to approve his financial scheme?

Something stinks here...

Maybe this guy should investigate and clear up the appearances of federal actions undertaken for private profit?

Whether the department will take the same approach under Chu's successor, MIT nuclear physicist Ernest Moniz, remains unclear.
I don't think that Moniz has a clue what his underlings are up to, but that's no excuse to let this federal land-taking scheme continue.

Clean Line's plans are a for-profit initiative masquerading as a political agenda.  And DOE's political agenda is favoring corporate interests over the interests of the citizens and consumers it is supposed to serve.  Let's clean the stink out of our federal Department of Energy!
5 Comments

Clean Line's Grain Belt Express Welcomed to Illinois

12/3/2014

7 Comments

 
Clean Line's Texas hucksters showed up in Illinois last night, and the citizens were there to meet them.
Outside the Church of the Nazarene Fellowship Hall, members of a grassroots protest group gathered to tell landowners of their opposition to the project. Inside the hall, company officials told of its benefits.
Which group do you think was telling the truth?  Hint:  One group was paid to be there by Clean Line, the other was there voluntarily.

Apparently there was lots of "misinformation" afoot, but only one group whined about "misinformation."  Guess which one?  It might be the one laboring under the misapprehension of the information deficit model.

The accompanying picture is a classic:  crowds of disenchanted landowners, some with arms folded, staring down the "clean" employee performing a song and dance in front of a company poster at an "information station."

The divide and conquer routine isn't working, Clean Line.  These folks got the jump on you.

Silly Clean Line routed their project through land owned by a local attorney.


"They are filing for expedited review with the (Illinois Commerce Commission) which provides for limited time for landowners to object and even shorter filing periods, which constrains ability to have fair and full hearings insuring that due process rights of each landowner are protected," Probst said.
"Our firm is looking into calling a meeting of landowners and invite other interested parties to discuss what options are available to the landowners of Shelby County," the lawyer added.
Ooopsy, Clean Line!  Why the hurry?  Hoping that you can ram this project through approvals at the ICC before the landowners organize enough to seek legal counsel?  Too late!

Bravo to the citizens of Illinois who have worked so hard to prepare for Clean Line, as well as to all the experienced Clean Line opponents who traveled to the meeting to help out.  What an auspicious beginning!
7 Comments

What Society Can Learn From Dr. Luther Gerlach

12/2/2014

3 Comments

 
A while back, I shared a little bit about Dr. Luther Gerlach and his work studying public response to electric transmission projects and how it produces debate about and shapes our energy future.  I included a link where you could download his short film, Grassroots Energy.

Now I'd like to share more about this amazing man, how he works, and how he created Grassroots Energy. 
Luther and Ursula Gerlach doing research in early 1970s on a protest of long haul truckers against high cost of their diesel fuel.  They made a 16mm film of the truckers' strike.
Dr. Gerlach explains how and why Grassroots Energy was made:
In the late 1990s, I made 12 videos for a distance learning version of my course Ecological Anthropology at the University of Minnesota, Twin Cities. I made these with the assistance of my wife, Ursula, my colleague Paul Eide in University Media Resources, and research assistant Tis Stringer.  To make these videos, we used 16 mm movie film, 35 mm slide/still film, and audio tape that Ursula and I had taken over years of anthropological field research in the USA, Kenya, Germany, and other places.  Our practice has been to complement written note taking with film and audio recording during this field research.  We draw upon our film and tape library to present lectures in class and also to make films and videos for use in class and in distance learning.  In recent years, we have digitized film and analog tape to make programs that can be presented via computer. 

It is thus that we made the Ecological Anthropology program Grassroots Energy.  I introduce and then conclude the movie with still photos and voice over narration. The movie itself is 27 minutes long, originally a 16 mm film.  We filmed during our field research.  We began research and recording in August 1974, shortly after farmers and townsfolk in West Central Minnesota learned that Cooperative and United Power had applied to state authorities for permits to build a +/-400kVDC line from a mine mouth plant in North Dakota across their land to a AC converter facility in a Minneapolis suburb.  We continued research and recording through the construction and energizing of the line and early response in 1980.  The film focuses on the period 1976-1978, when resistance to the line was most intense and widespread. 

Filming in the field and making slide shows and movies in the era before digital imaging presented problems not experienced by the users of digital cameras.  Instead of being able to take countless pictures and see the results immediately, one had to ration film and wait until processing to determine if one “got it or not.”  One had to keep film – and batteries - cool in the summer and warm in the winter.  And it was obvious to all that one was taking pictures or recording audio.  In any event, we observed the cardinal and ethical rule of anthropology: to get informed consent of those photographed.  

Before we released the film about the CU transmission line issue and resistance to it, we showed it to those involved in the resistance. 

A citizen’s organization in Wisconsin concerned with electricity production, distribution and use asked me if it could show the Grassroots Energy movie for a fundraiser.  After some deliberation, I agreed.  I then also agreed that a blog concerned with electricity transmission issues could provide access to this movie.  Further, I have included clips from the movie as well as other information about the CU case in a presentation to a workshop on transmission held in part by Edison Electric Institute.

I am now working to make available more of my published and unpublished material, print and audiovisual, on transmission and other energy issues.

Luther P. Gerlach, PhD
Professor emeritus of Anthropology, University of Minnesota

Biosketch

My studies of public response to electricity transmission lines is part of my broader study of the interplay of social movements and established orders in the management of technological and ecological risk and resource use locally, regionally and globally.  Thus, I examine how the interplay between advocates and opponents of transmission grid expansion produces debate about the energy future and shapes this future.

I have studied social movements, ecological adaptation, and related cultural change in the USA, Germany, and along the Kenya coast.  Following undergraduate and graduate study at the University of Minnesota, I served as a US Army officer in the Far East and a US government researcher in Germany. I then attended the University of London, particularly its School of Oriental and African Studies and also its London School of Economics, receiving certificates in African Law(Islamic Law Option) and Swahili, and a PhD in Cultural Anthropology (1960), following field research in Kenya.  In addition to my professorship in Anthropology at the University of Minnesota, I have been visiting professor at the Environmental Quality Lab of the California Institute of Technology, the Aspen Institute of Humanistic Studies, Oak Ridge National Laboratory, Science Center, Berlin, Germany.
If you haven't watched the film yet, you can download it here.

Luther's research, writings and film come closest that I have ever seen to capturing the feelings and purpose of people and groups who oppose transmission lines.  He has an understanding and appreciation for both sides of the energy debate, and studying his work should propel us along toward solutions. 

Instead, it appears that we are poised to make the same mistakes about centralized renewables that we made with centralized fossil fuel generation decades ago.  Why must the few sacrifice for the many when there are better solutions available?  Only when we understand social movements and energy equality can we learn from history and stop making the same mistakes over and over.

Dr. Gerlach has a huge body of work, some of which I've had the pleasure to read and ponder, and I hope he continues to make more of his published and unpublished works available.  There's so much to be learned!

Some of Dr. Gerlach's publications pertinent to social movements and energy for further reading:


Gerlach, Luther P, 2014. Public Reaction to Electricity Transmission Lines, Reference Module in Earth Systems and Environmental Sciences, Elsevier, 2014. 21-Mar-14 doi: 10.1016/B978-0-12-409548-9.09111-9.

Gerlach, L. P. (1999). The structure of social movements: Environmental activism and its opponents.  In Waves of Protest: Social Movements since the Sixties.  (J. Freeman and V. Johnson, Eds.), pp. 85–97. Rowan & Littlefield, NY

Gerlach, Luther P., and David Bengston. 1994. “If Ecosystem Management Is the Solution, What Is the Problem?” Journal of Forestry 92, no. 8 (August): 18–21.

Gerlach, L. & Palmer, G. (1981). Adaptation through evolving interdependence, pp 323-381 in Nystrom P.C, & Starbuck W.  Handbook of organizational design, vol 1. Adapting 0rganizations to their environments. New York, Oxford Press

 Gerlach, Luther P. (1979). Energy Wars and Social Change, in Predicting Sociocultural Change, Susan Abbot and John van Willigen, eds. Southern Anthropological Society Proceedings #13. Athens: University of Georgia Press 

Gerlach, L.P. 1978  Gerlach, Luther P. (1978). “The Great Energy Standoff.” Natural History 87 (January).

Gerlach, Luther P., and Virginia H. Hine. 1973. Lifeway Leap: The Dynamics of Change in America. Minneapolis: University of Minnesota Press.

Gerlach, Luther P., and Virginia H. Hine. 1970. People, Power, Change: Movements of Social Transformation. Indianapolis: Bobbs-Merrill.

 Gerlach LP and Eide P (1978) Grassroots Energy, 16-mm 27- minute, sound, color film. University of Minnesota Media Resources. Distributed by Penn State University Film.

We all owe Dr. Gerlach and his wife many thanks for their capable documentation and thoughtful commentary on our energy wars.  Now, let's do it better this time around as we move toward a cleaner, more democratic energy future!
3 Comments
<<Previous
Forward>>

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.